Making light work of your energy savings

Call us on 01455 552 511

Full Lighting And Electrical Installation For BDM Logistics, Nottingham

View All Catgories

Quick Read

BDM, specialists in worldwide logistics for the beauty industry, required a full lighting and electrical upgrade to support its expanding operations. The goal was to create a sustainable, efficient, and compliant electrical infrastructure that could handle current and future demands.

Project Brief

ECO UK Group was selected to deliver a lighting and electrical solution covering:

  • LV mains and sub-distribution systems
  • High-performance Pegasus LED warehouse lighting
  • Emergency lighting compliant with BS5266
  • Dedicated power supplies for HVAC, machinery, and office facilities
  • A future-proof design to accommodate operational growth

Scope of Works

Containment & Cable Management

Eco UK Group supplied and installed over 1,500m of ladder racks, trays, and basket for power, lighting, HVAC, and data cabling. This infrastructure ensures long-term durability and simplified maintenance.

LV & Mains Distribution Upgrades

Our electrical installation included:

  • New 400A sub-distribution panels with individual metering
  • 16-way and 12-way TPN distribution boards to serve operational zones
  • Specialist supplies for MHE charging, sprinkler systems, and HVAC plant

 

Energy-Efficient Warehouse Lighting

Using our Pegasus high-bay LED lighting, we provided:

  • 1,516m of 4-pole busbar for lighting distribution
  • 221 LED fittings with occupancy sensors and dimmable functionality
  • 58 emergency light fittings with key-switch test facility

This system delivers maximum illumination with reduced energy costs.

Full Lighting and Electrical Installation for BDM Logistics, Nottingham

Warehouse Power Infrastructure

Dedicated Circuits for material handling equipment, packing bench stations and sprinkler control system were installed for operational efficiency

HVAC Power Provision

We delivered complete electrical provision for the air handling units, fan coil units, destratification fans, and HVAC control systems, enabling effective climate control across the warehouse.

Ladder - Lighting

Office Power & Communications

The new comms room was fitted with dedicated AC and data supplies, dado trunking, and separate power circuits for both security and general office use.

Sustainability & Compliance

All works were carried out to BS7671, BS5266, and BS5839 standards. The installation reduces energy use through LED technology, HVAC time controls, and efficient power distribution.

Project Outcomes

  • Improved operational efficiency
  • Reduced long-term energy costs
  • Fully compliant with UK electrical regulations
  • Scalable infrastructure for future expansion
  • Delivered on time and within budget

About ECO UK Group

At ECO UK Group, we deliver end-to-end M&E services across the UK — from CAD design to installation and aftercare. Our specialities include warehouse lighting installation, electrical contracting, and sustainable energy solutions such as solar power integration.

Racking Aisle
Pegasus LED Lighting

For more on our Pegasus LED lighting, contact us on 01455 552511 or to find out more about our electrical solutions, visit www.ecogroup.com